Planning v4.1: record the v1.0.0 release, and plan v1.1
Documentation only. No product code, requirement, acceptance test or
schema changes.
Post-release correction. v4.0 was written before the closeout commit was
signed (432f041), main was fast-forwarded to it, and the signed v1.0.0 tag
was pushed. Current-state wording now says so in README.md,
planning/README.md, BUILD-MILESTONES.md and VERSION.md. BUILD-MILESTONES.md's
header had been stale since M8. The M11 report is not edited: its §T
records the state at closeout.
v1.1 plan. planning/V1.1-PLAN.md triages the post-v1 backlog and the other
recorded v1 residual risks, and orders them into work packages, not
milestones:
- A1: a context-window safety reserve, plus reporting a turn the server
truncated
- A2: removing protocol echoes from stored narration, and a genre-neutral
state rule
- B: long-term memory retention that holds without help from state
- C: browser coverage of Retry, Save Points, correction, length, failure
and export download
- D: integrity_check on backups, and a warning when an export exceeds the
import limit
- E: WCAG 1.4.11 control-boundary contrast
Scheduled backups, the import limit, identity detectors and duplication
suppression move to v1.2; media adapters are future work. The first brief
to write is A1.
Co-Authored-By: Claude Opus 5 <noreply@anthropic.com>
Claude-Session: https://claude.ai/code/session_01VvegagkhuCZoFPdv4M1egY
This commit is contained in:
co-authored by
Claude Opus 5
parent
432f04100b
commit
ac465ed867
+42
-27
@@ -2,11 +2,14 @@
|
||||
|
||||
**This file is the index. Start here.**
|
||||
|
||||
**Current state:** Phase 0 complete; AI-DnD forked as the production base;
|
||||
**milestones M1 through M11 complete**. **M11 was accepted at its closeout
|
||||
(2026-09-14), and the v1 release gate passed** on the release-candidate tree.
|
||||
There is no further planned milestone. The signed closeout commit and any
|
||||
`v1.0.0` tag are separate events and the repository owner's to perform. M1-M6 were accepted on the dates below (M3 and M4: 2026-09-03;
|
||||
**Current state:** **v1.0.0 released on 2026-09-14. v1.1 planning has begun.**
|
||||
Phase 0 complete; AI-DnD forked as the production base; **milestones M1
|
||||
through M11 complete and closed**. M11 was accepted at its closeout
|
||||
(2026-09-14), the v1 release gate passed on the release-candidate tree, and the
|
||||
owner then signed the closeout commit (`432f041`), fast-forwarded `main` to it,
|
||||
and created and pushed the signed tag `v1.0.0` pointing at it. v1.1 development
|
||||
is on the `v1.1-development` branch, from that commit, and is planned in
|
||||
`V1.1-PLAN.md` as work packages, not milestones. M1-M6 were accepted on the dates below (M3 and M4: 2026-09-03;
|
||||
M5: 2026-09-04; M6: 2026-09-06). M5 and M6 were each accepted only after an
|
||||
independent review found a real defect and a corrective pass fixed it.
|
||||
|
||||
@@ -46,13 +49,18 @@ The closeout repeated the browser, offline and identity runs on the exact
|
||||
release-candidate tree (`3652dc6`), and recorded the acceptance (report §S and
|
||||
§T). **The v1 release gate passed.**
|
||||
|
||||
**Not yet happened**, and each a separate event:
|
||||
- the owner signing the closeout commit;
|
||||
- merging to `main`, which still points at M10;
|
||||
- any `v1.0.0` tag.
|
||||
**The release, 2026-09-14.** The three events the closeout left to the owner
|
||||
have all happened:
|
||||
- the closeout commit is signed, as `432f041`;
|
||||
- `main` was fast-forwarded to `432f041`;
|
||||
- the signed tag `v1.0.0` points at `432f041`, and is pushed.
|
||||
|
||||
**There is no further planned milestone and no M12.** Post-v1 work is backlog
|
||||
(`BUILD-MILESTONES.md`, *Post-v1 backlog*).
|
||||
The M11 report's §T still lists the last two as not done. That table records the
|
||||
state at closeout and is deliberately left as written.
|
||||
|
||||
**There is no M12.** Post-v1 work is organised as **v1.1 work packages** in
|
||||
`V1.1-PLAN.md`, which triages the *Post-v1 backlog* recorded in
|
||||
`BUILD-MILESTONES.md`.
|
||||
|
||||
**Package version:** see `VERSION.md`, which records what each revision changed
|
||||
and why.
|
||||
@@ -122,7 +130,8 @@ Two standing qualifications:
|
||||
| `SECURITY-THREAT-MODEL.md` | The trust boundary, and the inference endpoint policy as implemented. |
|
||||
| `MEDIA-EXTENSION-CONTRACT.md` | The contract future image/video/audio/TTS/STT work must fit. |
|
||||
| `BROWSER-UX-SPEC.md` | The browser surface, and what is deliberately not in it. |
|
||||
| `BUILD-MILESTONES.md` | M1-M11, what each delivers, what is done, and the notes each milestone leaves its successors. |
|
||||
| `BUILD-MILESTONES.md` | M1-M11, what each delivers, what is done, and the notes each milestone leaves its successors. Closed history; not extended. |
|
||||
| `V1.1-PLAN.md` | **Post-v1 work.** The triaged backlog, the ordered v1.1 work packages with acceptance criteria, the v1.1 release criteria, and what is deferred. |
|
||||
| `V1-ACCEPTANCE-TESTS.md` | The pass/fail contract v1 is measured against. |
|
||||
| `TEST-CAMPAIGN-FIXTURE.md` | The standard campaign the acceptance tests are run on. |
|
||||
| `VERSION.md` | Package revision history: what each closeout changed. |
|
||||
@@ -133,7 +142,8 @@ Two standing qualifications:
|
||||
1. This file.
|
||||
2. `SPECIFICATION.md`
|
||||
3. `TECHNICAL-DESIGN.md`
|
||||
4. `BUILD-MILESTONES.md` — find the milestone you are being asked to do.
|
||||
4. `V1.1-PLAN.md` — find the work package you are being asked to do.
|
||||
`BUILD-MILESTONES.md` is the v1 history behind it.
|
||||
5. `STORY-BRANCH-SEMANTICS.md`
|
||||
6. `DATA-MODEL.md`
|
||||
7. `CONTEXT-AND-MEMORY.md`
|
||||
@@ -185,7 +195,9 @@ that is the one the next milestone's planning has to consult:
|
||||
It stays in `reports/` after acceptance. The rotation moves a report to the
|
||||
archive when the next milestone's report is written, and after M11 there is no
|
||||
next milestone. Nothing here calls for moving it, so no new convention was
|
||||
invented to do so.
|
||||
invented to do so. `V1.1-PLAN.md` asks each v1.1 work package for a report of
|
||||
its own; when the first is written, it joins this one in `reports/` and the
|
||||
rotation is decided then.
|
||||
|
||||
M9's and M10's reports both moved to `archive/milestone-reports/` when this one
|
||||
was written. M9's had been kept here past its turn because M9 was unaccepted;
|
||||
@@ -337,27 +349,30 @@ Milestone M11 COMPLETE / ACCEPTED (2026-09-14)
|
||||
|
|
||||
v
|
||||
v1 release gate PASSED (2026-09-14)
|
||||
signed release commit and v1.0.0 tag:
|
||||
the repository owner's, not yet done
|
||||
|
|
||||
v
|
||||
Post-v1 backlog only; no milestone planned
|
||||
v1.0.0 RELEASED (2026-09-14)
|
||||
signed tag on signed commit 432f041;
|
||||
main points at the same commit
|
||||
|
|
||||
v
|
||||
v1.1 PLANNING (from 2026-09-14)
|
||||
branch v1.1-development; V1.1-PLAN.md
|
||||
work packages, not milestones
|
||||
```
|
||||
|
||||
## Stop Rule
|
||||
|
||||
**One milestone at a time. Do not begin a milestone before its brief exists.**
|
||||
**One work package at a time. Do not begin a work package before its brief
|
||||
exists.**
|
||||
|
||||
**Every planned milestone is complete, and M11 is accepted.** The v1 release gate
|
||||
passed on 2026-09-14 (M11 report §T).
|
||||
**Every v1 milestone is complete, M11 is accepted, and v1.0.0 is released**
|
||||
(2026-09-14, tag `v1.0.0` on `432f041`).
|
||||
|
||||
The next actions are the owner's:
|
||||
1. sign the closeout commit;
|
||||
2. decide on the `v1.0.0` tag, pointed at that signed commit.
|
||||
|
||||
Neither is a milestone. **Do not begin post-v1 work as though it were a v1
|
||||
milestone.** Anything after v1 starts from the *Post-v1 backlog* in
|
||||
`BUILD-MILESTONES.md`, with a brief of its own.
|
||||
**Do not begin post-v1 work as though it were a v1 milestone, and do not create
|
||||
M12.** v1.1 work is the ordered work packages in `V1.1-PLAN.md`. Each starts
|
||||
only from a coding brief of its own, and stops at its own boundary for review.
|
||||
The plan names the brief to write first.
|
||||
|
||||
All three questions the M8 debt raised against M9 are settled and recorded:
|
||||
the bundle carries historical context snapshots (`DATA-MODEL.md` §29); story
|
||||
|
||||