# ADR 008 — Complete Phase 0 Before Detailed Build Planning
|
|
|
|
**Status:** Accepted
|
|
|
|
## Decision
|
|
|
|
The project will complete repository research, validation, architecture selection, and critical prototypes before writing the detailed production implementation milestone plan.
|
|
|
|
## Context
|
|
|
|
Multiple candidate open-source projects already implement overlapping parts of the desired system. The correct build sequence depends heavily on which codebase is selected.
|
|
|
|
## Alternatives Considered
|
|
|
|
- write full implementation plan immediately,
|
|
- begin coding against the first plausible project,
|
|
- perform a bounded Phase 0 and then finalize the build plan.
|
|
|
|
## Reason
|
|
|
|
The third approach reduces speculative planning and prevents large amounts of rework.
|
|
|
|
## Consequences
|
|
|
|
- `BUILD-MILESTONES.md` remains intentionally high level during Phase 0,
|
|
- production coding should not begin unless explicitly authorized,
|
|
- Phase 0 ends with the final build plan.
|